Stone Harbor Maintenance Dredging Update

The Dredging project is on standby until complications with the dredging and dewatering of the dredged material can be resolved. The dredged material that was removed from the North Basin is contained within the geotextile tubes on the marina parking lot and is slowly dewatering. The Borough is working with the contractor to evaluate modifications to increase the dewatering rate for current and future materials.

Once dredging resumes, an updated basin schedule will be provided. We anticipate dredging at least one more basin during this phase of the contract. Phase 1 will be completed by March 31 at which time the Contractor will have demobilized from the site and restored the marina to its pre-existing conditions.

Please visit the Borough website, www.stone-harbor.nj.us on the “Home Page” under “Quick Links” for Back Bay Dredge Updates as they become available.